Dear Experts,
Lets say requirement against a material is 600 EACH. M using MRP type PD and lot size "EX". There is already Purchase Requisition of 500. When i will execute MRP , system will generate planned order of 100. But i want that system automatically remove previous PR i.e. 500 quantity and make new planned order of 600. so that number of PR's should be minimize. One scenario is simple which is to delete pending PR's before running MRP. I dont want this scenario. Can it possible to get this idea ?
Regards
Engr. Qazi Raheel Ahmed