I have Major Query for Proposed Delivery Dates in Purchase order & MRP generated Purchase Requisitions.
Problem Statement
My business Scenario is -->
Lets take an example, company in Europe and vendor based in Asia.
Vendor will ship the material only till Shipping yard in Asia. after Shipping yard they will send proforma Invoice by email as notification.
Take an example the Delivery time till shipping yard for Vendor is 10 day’s from the day of PO. --> in SAP this is Considered as Planned Delivery Time for Info-record.
lets take example as The Shipment Days are 45 Day’s from Asian Shipping yard to European Shipping yard.
From Shipping yard to plant it will take more 5 Days. --> in SAP this Is considered as GR processing time in Info-record.
SC margin key = 000 -- 0 day's.
Help Required for -->
1) Not Able to display the actual In-transit time of particular procurement for Asian Vendor. – There is No Field in Material Master to update In-transit time.
2) Incorrect data in evaluate the On time delivery report for vendor. – I have created Z T-code with calculations based on EKBE + EKET + Other.
3) in SAP GR processing time is in working day’s (5) in calendar but Planned delivery dates are weekly (7) day’s – incorrect data for Material availability.
Testing Data -->
I have tested this scenario with Info-record planned delivery time – 10 + 45 Day’s & GR processing time is 10 Days.
And with Info-record planned delivery time – 10 & GR processing time is 45 + 10 day’s.
Processed GR with 107 Movement, to proceed for Invoice.
There is no way out to display the Actual In-transit time.
Please Help me to fulfil this requirement.
Out Of scope Points -->
1) Inbound Deliveries
2) GR Based Invoice.
Best Regards,
Ninad