Dear Gurus,
our customer procures as certain group of materials as one lot together , physical inventory Goods Receipt occurs for the lotst & Goods issue for production is also done for the lots ,
but component mapping of that lot is essential in case of finding a defective part & for assignment of components to work center.
E.G : Material X is a whole lot that contains materials (Y,Z,A,B)
purchase order is done using material X e.g: 2 pcs (lots ) are needed for material X
goods receipt is done for the ordered 2 lots
goods issue for production is done using the whole lot as a unit of issue.
But in production we need to map materials Y,Z,A,B of the issued lot for material assignment to work centers & in case of any defective material of them : e.g part Z is found to be defective & needs to be returned to the vendor.
How can we map that scenario in SAP