Fixed Cost Activities

$
0
0

Hi all,

 

Is it possible to plan a cost centre/activity type value (via KP26) that posts costs to a PM/CS order with a quantity of 1 irrespective of what quantity the user enter in the confirmation document?

 

Example:

The CC/AT value is £100/hour.

If the user posts 1 hour in the confirmation document the actual cost                = £100

If the user posts 10 hours in the confirmation document the actual cost also      = £100

 

Note: we cannot change the number of hours the users enter in the confirmation document.

 