Hi all,
Is it possible to plan a cost centre/activity type value (via KP26) that posts costs to a PM/CS order with a quantity of 1 irrespective of what quantity the user enter in the confirmation document?
Example:
The CC/AT value is £100/hour.
If the user posts 1 hour in the confirmation document the actual cost = £100
If the user posts 10 hours in the confirmation document the actual cost also = £100
Note: we cannot change the number of hours the users enter in the confirmation document.
PeteA