Planned order shouldn´t consider planned delivery time

$
0
0

Hi Gurus,

 

I have production plant A and sales plant B.

 

In plant B the SKU is marked as external procurement, with planned delivery time of 25 days (because of ATP).

 

In plant A the SKU in produced internally and have a production time of 25 days also.

 

When I run MRP it´s creating the inicial basic date of the transfer planned order to 25 days before requirement and it also creates the production planned order more 25 days back.

 

I wan´t to know if it´s possible to MRP not consider the Planned Delivery Time at the plant B and create the transfer planned order with no time at all. Meaning that the planned order should have the same date as the requirement at sales plant.  Already check OMEW and OMDT.

 

FYI, I have to keep the PDT in the sales plant otherwise I can´t run the ATP for sales order.

 

Tks all in advance.


Best Regards,

 

Felipe