During copying of a network constraint dates get lost

$
0
0

Hi experts,

 

When I copy a network in the project builder and when the activities have constraint dates, the constraint dates get lost. In the copied network the activities will have no constraint-dates.

 

Is there a way to keep the activity constraint-dates during network copying?

 

Are there maybe different ways of copying in CJ20N a network? I dragged the network onto the worklist and dragged it then from there back onto a WBS element in order to copy it.

 

Thanks,

GM