Hi experts,
When I copy a network in the project builder and when the activities have constraint dates, the constraint dates get lost. In the copied network the activities will have no constraint-dates.
Is there a way to keep the activity constraint-dates during network copying?
Are there maybe different ways of copying in CJ20N a network? I dragged the network onto the worklist and dragged it then from there back onto a WBS element in order to copy it.
Thanks,
GM