Dear Experts,
I have implemented milestone confirmation scenrio. For example, if a material has 4 Operations in routing and i have assigned last operation as milestone operation. and i do confirmation only on milestone operation it automatically carry out confirmations on remaining all operations. My question is that, I only want to allow doing confirmations on Milestone Operation and system shouldn't allow to carry out Confirmations otherthan on Milestone operation. How is it possible????