Dear Experts,
We are running MRP based on planning time fence for the next rolling three months plan around 20th to 25th of every month.
The no of days fenced would be around 17 to 22 days based on the actual MRP running date.
So after MRP run, the delivery schedules which were generated in previous month MRP will not get disturbed in the PTF period due to current MRP run.
Our concern is while doing MRP analysis, there are few materials for which PR has got generated during total MRP RUN.
But when we execute single level MRP, schedule lines are getting generated correctly.
There is no change in MRP related parameters during the period and following has been verified.
1. Source list is valid on MRP run date and having the sch agmt no and with 2 indicator.
2. Scheduling agreement is having validity date.
3. Quota master has been maintained with 80:20 for 2 vendors.
4. In the OPPQ settings, shipping notifications are taken in to account for Rescheduling as we are using inbound delivery.
We are getting this issue every month for few part nos and we are unable to figure out the exact reasons for this.
Request you to throw some light on this to fix the issue or missing configuration if any.
Regards
S Balaji